Active Bid Opportunities
Bid Information
25-02
Cal883416C
Request for Bids
Calhoun
Description
In general, the work involves, but is not limited to, selective clearing, excavation and grading, along with tile and outlet structures, riprap placement, and seeding. The project also includes installation of a wet well and pump system. This project includes around 118,600 cubic yards of earthwork, 2.756 linear feet of various tile installation, one aluminimum toe wall, 653 tons of riprap along with 60 tons of erosion stone, and 20.6 acres of seeding. The estimated construction cost range for this project is $800,000 to $900,000.
Completion Dates:
Construction: November 1, 2025
Buffer Seeding: December 15, 2025
Agency Information
009
Agriculture and Land Stewardship
502 E 9TH ST
Des Moines, IA 50319
Contact Information
Valid Dates
2/2/2025 8:17:00 AM
3/5/2025 8:17:00 AM
Documents/Attachments